Frequent updates on progress for all City Engineer capitol improvement projects including schedule changes, and other relevant information to property owners, citizens, visitors, or people who are simply curious!  Check back often.  Subscribe below to be notified when changes are made/updates are posted.  Your information will remain private.

Thanks for submitting!

Continued Progress

CCI paved the west half of 17th Street along the top 1/3 of the hill, and have begun to prep the east half for next week.


Miller is finishing up with water main as they have been switching over the properties along the bottom of the hill to their new services. They will move from water main to storm sewer work next week, starting at Rte 84 and heading south.


MidAmerican has completed all utility relocations.

7 views0 comments

Recent Posts

See All

CCI will be completing the mainline paving of 17th Street tomorrow (Friday), as they pave the east half of the missing link between the bottom and top of the hill. Backfilling behind the back of curb