17th Street to Open Today (11/15/23)
top of page
Progress Updates (Blog)
Frequent updates on progress for all City Engineer capitol improvement projects including schedule changes, and other relevant information to property owners, citizens, visitors, or people who are simply curious! Check back often. Subscribe below to be notified when changes are made/updates are posted. Your information will remain private.
The contractor has been diligently working to finish up the final missing pieces and cleaning up the project area this week. Seeding...
Brian Boelk
Nov 9, 20231 min read
The Last Big Pour!!!!
CCI will be completing the mainline paving of 17th Street tomorrow (Friday), as they pave the east half of the missing link between the...
133 views1 comment
Brian Boelk
Nov 3, 20231 min read
Paving Day!
CCI will be paving the remaining missing piece on the west side of 17th Street today! The plan is to then follow by prepping the east...
78 views0 comments
Brian Boelk
Oct 25, 20231 min read
Looking Ahead
With the intent to have the project completely wrapped up and finished by Thanksgiving, here is a look at upcoming items the Contractor...
180 views0 comments
Brian Boelk
Oct 20, 20231 min read
Getting Closer and Closer
CCI completed paving the East side of 17th Street today! CCI will begin working on installing new driveways along the east side next...
150 views0 comments
Brian Boelk
Oct 13, 20231 min read
When it Rains, it Pours!
Well, just as we were getting some momentum in paving the final pieces of 17th Street, the drought decided to come to an end of course....
116 views0 comments
Brian Boelk
Oct 13, 20231 min read
Core Out of East Side of 17th St!
CCI will begin the core out the East side of 17th Street on Saturday, October 14th, weather permitting. If weather does not allow for...
14 views0 comments
Brian Boelk
Oct 6, 20231 min read
The Road to Completion
Paving of the west half of 17th Street started early this morning by CCI as they took on the cooler temps and a little bit of rain. The...
164 views0 comments
Brian Boelk
Oct 3, 20231 min read
Paving Update!
CCI will be paving the west side of 17th Street this Friday. Please note to take caution while travelling in this area and try to stay...
56 views0 comments
Brian Boelk
Sep 29, 20231 min read
One Step At A Time
We continue to get closer and closer to paving the remaining roadway on 17th Street! This week, Miller completed the storm sewer...
134 views0 comments
Brian Boelk
Sep 22, 20231 min read
What to Expect Next Week (9/25 thru 9/29)
CCI will continue working on removals along the west side of 17th Street still Monday, while MidAmerican Gas installs new gas service to...
111 views0 comments
Brian Boelk
Sep 17, 20231 min read
Upcoming Week - 9/18/23
CCI will start the core out on the west side of 17th Street, starting at Route 84 and heading south. Anticipate to get about 500' of...
29 views0 comments
Brian Boelk
Sep 15, 20231 min read
End of Week Project Update
Final water main construction activity was completed Tuesday (09/12/2023), no more scheduled shut offs of water are expected for this...
31 views0 comments
Brian Boelk
Sep 8, 20231 min read
Gaining Momentum
This week CCI paved the drive to the water tower, the final driveway on 7th Ave, and the east flume on the 17th Street hill. Miller is...
68 views0 comments
Brian Boelk
Sep 5, 20231 min read
Impacts to 17th Street - Bottom of Hill
Miller (utility contractor) will begin working on storm sewer installation this week within 17th Street, working between Rte 84 and the...
36 views0 comments
Brian Boelk
Aug 30, 20231 min read
August 31st Notification
Miller will be working on the pressure reduction valve (water pit) on the 17th Street hill tomorrow (08/31/2023). There is no anticipated...
60 views0 comments
Brian Boelk
Aug 29, 20231 min read
Moving Along
The west side concrete drainage flume and 7th Ave radii were poured today. Subbase on teh east portion of the hill is being prepped, with...
16 views0 comments
Brian Boelk
Aug 26, 20231 min read
Continued Progress
CCI paved the west half of 17th Street along the top 1/3 of the hill, and have begun to prep the east half for next week. Miller is...
8 views0 comments
Brian Boelk
Aug 23, 20231 min read
Paving......Coming in Hot
Despite the extreme temps, the contractors have continued to proceed and progress. Tomorrow (Thursday) CCI will be paving the west half...