Frequent updates on progress for all City Engineer capitol improvement projects including schedule changes, and other relevant information to property owners, citizens, visitors, or people who are simply curious!  Check back often.  Subscribe below to be notified when changes are made/updates are posted.  Your information will remain private.

Thanks for submitting!

Writer's pictureBrian Boelk

End of Week Project Update

Final water main construction activity was completed Tuesday (09/12/2023), no more scheduled shut offs of water are expected for this project.

CCI worked this week to grade behind all of the completed paving at the top of the hill, and Miller has storm sewer is installed up to Big River Customs.

CCI will begin removing pavement on the West side of 17th Street starting near TBK Bank. Residents will still have access down 17th Street on the East side of the road. Thank you for your continued support as project construction continues.