Frequent updates on progress for all City Engineer capitol improvement projects including schedule changes, and other relevant information to property owners, citizens, visitors, or people who are simply curious!  Check back often.  Subscribe below to be notified when changes are made/updates are posted.  Your information will remain private.

Thanks for submitting!

Writer's pictureBrian Boelk

Gaining Momentum

This week CCI paved the drive to the water tower, the final driveway on 7th Ave, and the east flume on the 17th Street hill.


Miller is installing the new storm sewer at a good pace, and finished near Thai Flavors today. They will continue to install the storm sewer south next week.


CCI will be backfilling all the new pavement on top of the hill next week, as they plan to begin paving 17th Street starting at Rte 84 the week of Septebmer 18th.


There is a schedule water shut-off for a select few properties Monday, September 11th. The Village has been communicating and coordinating with those properties impacted by the shutoff.


Thank you and have a great weekend everyone.









68 views0 comments

Recent Posts

See All

The Last Big Pour!!!!

CCI will be completing the mainline paving of 17th Street tomorrow (Friday), as they pave the east half of the missing link between the...