With the intent to have the project completely wrapped up and finished by Thanksgiving, here is a look at upcoming items the Contractor will be working on:
Finishing driveways/approaches the next couple of days this week.
Earthwork fill, grading, and installation of ditch checks on west side to follow.
Subdrain and Paving of missing piece on west side of 17th Street next week.
Subdrain and Paving of missing piece on east side of 17th Street following.
Final grading, topsoil, and seeding.
Thank you.