Frequent updates on progress for all City Engineer capitol improvement projects including schedule changes, and other relevant information to property owners, citizens, visitors, or people who are simply curious!  Check back often.  Subscribe below to be notified when changes are made/updates are posted.  Your information will remain private.

Thanks for submitting!

Writer's pictureBrian Boelk

Moving Along

The west side concrete drainage flume and 7th Ave radii were poured today.


Subbase on teh east portion of the hill is being prepped, with the intent to pave on Thursday.


Miller is finished the last water services on the west side of the road. They will begin to start working on the water meter pit (vault) tomorrow or Thursday.


16 views0 comments

Recent Posts

See All

The Last Big Pour!!!!

CCI will be completing the mainline paving of 17th Street tomorrow (Friday), as they pave the east half of the missing link between the...