We continue to get closer and closer to paving the remaining roadway on 17th Street!
This week, Miller completed the storm sewer installation, which also then wrapped up all the public utility work for this project. In addition, MidAm came back in and finished up the installation of on gas service that had yet to be completed. MediaCom still needs to relocate utility on East side of roadway, and final plans were submitted Monday for that work.
CCI continues to to prepare for the paving of 17th Street by finishing rock subbase installation and final grading. They plan to pave next week and we will continue to update you as we know a more specific date and any additional potential traffic impacts.