Potential coring out of remaining driveway on 7th Avenue early in the week, with paving of such driveway to follow. MidAmerican Energy is scheduled to be moving forward with pole relocate on the 17th Street hill and at the top of hill. CCI will continue to remove existing 17th Street north (down the hill) and begin to prepare for future paving and utilities. Miller will continue working on watermain, which is going slowly due to constraints/impacts made by bedrock.
top of page
Progress Updates (Blog)
Frequent updates on progress for all City Engineer capitol improvement projects including schedule changes, and other relevant information to property owners, citizens, visitors, or people who are simply curious! Check back often. Subscribe below to be notified when changes are made/updates are posted. Your information will remain private.