CCI will start the core out on the west side of 17th Street, starting at Route 84 and heading south. Anticipate to get about 500' of core out completed and install subdrain and rock subbase this coming week . The following week they look to complete the rest of the way to where they stopped paving going down the hill.
Miller will continue to install storm sewer, continuing to head south on 17th Street.