Frequent updates on progress for all City Engineer capitol improvement projects including schedule changes, and other relevant information to property owners, citizens, visitors, or people who are simply curious!  Check back often.  Subscribe below to be notified when changes are made/updates are posted.  Your information will remain private.

Thanks for submitting!

Upcoming Week - 9/18/23

CCI will start the core out on the west side of 17th Street, starting at Route 84 and heading south. Anticipate to get about 500' of core out completed and install subdrain and rock subbase this coming week . The following week they look to complete the rest of the way to where they stopped paving going down the hill.


Miller will continue to install storm sewer, continuing to head south on 17th Street.

29 views0 comments

Recent Posts

See All

The Last Big Pour!!!!

CCI will be completing the mainline paving of 17th Street tomorrow (Friday), as they pave the east half of the missing link between the...